Street Should Have Closed before FIU Bridge Collapse, Feds Say

PEDRO PORTAL
/
MIAMI HERALD
An aerial photo shows the fallen Florida International University bridge. It had developed cracking in the days before the collapse on March 15, 2018.

In a damning new report, federal work-safety investigators conclude that engineers in charge of design and construction of the ill-fated Florida International University pedestrian bridge should have shut down Southwest Eighth Street because of growing cracks in the structure, but failed to recognize the span was in danger of imminent collapse due to design errors.

The 115-page report by the Occupational Safety and Health Administration, obtained Tuesday by the Miami Herald, finds plenty of blame to spread around for the collapse of the bridge last year while under construction.

The report details a catalog of errors ranging from a “deficient” design by Tallahassee-based FIGG Bridge Engineers that led to structural failure, to inadequate oversight by two engineering consulting firms that were supposed to act as a backstop on design and construction, Louis Berger and Bolton Perez and Associates, and a fatal attempt by FIGG to close the cracks that triggered the collapse.

Read more at our news partner the Miami Herald.